El Rancho Unified School District

KYA is proud to partner with El Rancho Unified School District to provide modernizations funded through Measure ER, a $200 million bond measure, was put on the ballot to:

  • Modernize and transform El Rancho High School to 21st century educational standards.

  • Upgrade our schools to train students with modern skills for jobs of the future.

  • Repair leaky and aging roofs, remove asbestos and other hazardous materials, upgrade heating and air conditioning and replace outdated plumbing, wiring and sewer systems.

  • Improve school security and safety.   


El Rancho High School Modernization:

El Rancho High School

2-Story CUUBE building and Amphitheater

Project Starting Soon…


MPR Modernization Projects:

Rivera Elementary School

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

March 2025

KYA completed a temporary lunch shelter at Rivera Elementary to replace the MPR during construction. Safety zoning and fencing has commenced to prioritize the safety of students during construction which will be starting next month.


Durfee Elementary School

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

March 2025

KYA completed a temporary lunch shelter at Durfee Elementary to replace the MPR during construction. Safety zoning and fencing has commenced to prioritize the safety of students during construction which will be starting next month.

Ground Breaking Ceremony coming soon…


Valencia Academy of the Arts

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

March 2025

KYA completed a temporary lunch shelter at Valencia Academy of the Arts to replace the MPR during construction. Safety zoning and fencing has commenced to prioritize the safety of students during construction which will be starting next month.

Ground Breaking Ceremony coming soon…


South Ranchito Dual Language Academy

MPR Modernization & Shade Construction

Start Date: March 2025

Estimated Completion Date: January 2026

March 2025

KYA completed a temporary lunch shelter at South Ranchito Dual Language Academy to replace the MPR during construction. Safety zoning and fencing has commenced to prioritize the safety of students during construction which will be starting next month.

Ground Breaking Ceremony coming soon…